At this time of Thanksgiving, we are thankful for our construction team, and all that they are doing to build your beautiful new home!
This week’s update:
- Zone 1 HVAC and plumbing is complete on floors 3 and 4. Electrical rough-ins are completed on floor 4, wire is being pulled on floor 3 and boxing is occurring on floor 2.
- Insulation has begun in Zone 1. Non-structural garage walls have been started.
- Zone 2 Walls are framed on floors one and two, and are being installed on Floor three. Windows are being installed on floor three. All framing is on schedule to be completed next month.