All wall framing in the building is complete as of today, and we are starting roof trusses in zone 2. In zone 1, HVAC rough-ins, plumbing and water lines are 100% complete, and ducting has started on the 4th floor. Electrical rough-ins for zone 1 are complete for floors 2-4 and are in process for floor 1. Insulation is finished for zone 1 floors 4 and 3 and is in process on floor 2. Drywall has started in zone 1 and we are currently sheet rocking floor 3, and soffits are being framed-in on floor 4. Brick work is starting on the exterior of the building on Monday, December 10th. Everything remains on schedule for completion in May!