Central Village Construction

Central Village Construction Update

All wall framing in the building is complete as of today, and we are starting roof trusses in zone 2. In zone 1, HVAC rough-ins, plumbing and water lines are 100% complete, and ducting has started on the 4th floor. Electrical rough-ins for zone 1 are complete for floors 2-4 and are in process for floor 1. Insulation is finished for zone 1 floors 4 and 3 and is in process on floor 2. Drywall has started in zone 1 and we are currently sheet rocking floor 3, and soffits are being framed-in on floor 4. Brick work is starting on the exterior of the building on Monday, December 10th. Everything remains on schedule for completion in May!

Central Village Construction Central Village Construction