If you have been watching the progress on our onsite camera, you already know how much progress is being made!
- Framing is 100% completed on floor one, both zones 1 and 2!
- Exterior and interior walls are set and framing is 80% completed on floor two, zone 1.
- Truss work is completed on floor two, zone 1.
- Plywood flooring is completed on second floor, zone 2.
- Plywood flooring is completed on third floor, zone 1 and exterior walls are starting to be set in place.
- Stairway B is complete to the third floor.
- The garage concrete slab in completely installed.
- The plumber is onsite laying out the first and second floor. Core drilling began yesterday.
- HVAC and the electrician have been onsite this week doing layout work.
Looking ahead, we are on track to begin roofing in early April. Have a great weekend!