Hello Zvago Lake Superior members!
Here is this week’s update:
- Electricians – Fixtures are being installed on the 4th and 3rd floors of Zone One. They are also working in the garage.
- Plumbers – Gas lines are being installed in the garage and for the MagicPaks.
- HVAC – Unit duct work is underway on the 2nd floor of Zone Two.
- Sprinklers – All units are completed and work is underway in the garage.
- Siders – Siding is being installed on multiple sides of the building, including the plaza.
- Framers – Deck frames and bases are being installed.
- Sheet Rockers – Sheetrock is being installed on the 2nd floor of Zone Two.
- Tapers – Taping is completed on the 4th floor of Zone Two and are starting on the third floor.
- Painters – Painting is completed in all of Zone One units, stair towers, and corridors. Next they will be starting on the 4th floor of Zone Two.
- Flooring – Floors are being installed in the last three units of Zone One, and tile work is underway in the bathrooms.