Construction Site

Lake Superior Construction Update

We have a great team constructing this community!

Everything is on schedule for Zvago Lake Superior.  If you drive by the site, or look at this week’s pictures, you will notice that the retaining walls are completely finished!  Also, the last of the footings were poured this week.  We are currently about 40% finished with the foundation block and looking to be completely done with the block by November 29th.  The precast for the main floor is scheduled for delivery in early December.  On Monday we will be bringing the main driveway up to grade.  Despite the cold, everything is moving along!

 

Click here to check out the construction progress.

Duluth Construction Site Duluth Construction Site Duluth Construction Site Duluth Construction Site Duluth Construction Site Duluth Construction Site