Things remain on schedule!
-
- The driveway has had its final sub base course installed, and site work will resume in the spring.
- The masonry work on the garage walls is 75% complete.
- Over the next two weeks we will be finishing up the masonry work, and beginning the precast plank over the garage. (This will be the first layer of the first floor community spaces and units!)
If Mother Nature cooperates, we will be framing units for Christmas this year!