Construction Site

Lake Superior Construction Update

Check out the construction progress here!

Things remain on schedule!

    • The driveway has had its final sub base course installed, and site work will resume in the spring.
    • The masonry work on the garage walls is 75% complete.
    • Over the next two weeks we will be finishing up the masonry work, and beginning the precast plank over the garage.  (This will be the first layer of the first floor community spaces and units!)

If Mother Nature cooperates, we will be framing units for Christmas this year!

Click here to check out the construction progress.

Construction Site Construction Site Construction Site Construction Site Construction Site Construction Site