A chilly hello Zvago Lake Superior members!
Construction is moving right along!
- We have finished up with the majority of the framing work on the first floor.
- Work has started stair tower B.
- Exterior walls with windows are going up on second floor zone one.
- Interior walls on second floor zone one have been started and we have set a goal of completing the walls by Monday.
- The garage underground electrical and plumbing is complete.
- We will start pouring the garage slab on Monday.
- Our plumbers and HVAC are scheduled to start in two weeks.
Have a Happy Valentine’s Day!